I-75 from Pasco County Line to South of US98/SR50/Cortez Design-Build - Middlesex Corporation
Florida Department of Transportation

I-75 from Pasco County Line to South of US98/SR50/Cortez Design-Build

Hernando County, FL

Improvements to 5.5 miles of I-75 (SR 93) from the Pasco/Hernando County Line to South of US 98/SR 50/ Cortez Boulevard in Hernando County.

The improvements on this project included roadway, structures, drainage, geotechnical, traffic control, utilities, subsurface utility engineering, intelligent transportation systems and signing, and pavement marking . Other associated efforts included public involvement, hazardous materials, right-of-way, utility coordination, and environmental permitting. Construction of this project resulted in added capacity, safety, and mobility to the corridor.

Project Numbers

$35M

Project value

13,000 Tons

Temporary asphalt pavement

310,000 CY

Embankment

100,000 Tons

Limerock base construction

60,000 Tons

Superpave asphalt pavement

350,000 SY

Grading and sodding