Brightline Zone 2 GOAA Rail Infrastructure
Brightline Trains LLC has secured the rights to operate an intercity passenger rail system connecting Miami to Orlando. Contract C-202 Zone 2 comprises the construction of a dual track rail infrastructure through Orlando International Airport.
The new track route crossed a number of airport roadways and passed under taxiways and the existing airport people mover track. This required new airport infrastructure and modification to the existing infrastructure. Foundations for a future light rail corridor were also installed.
Brightline accepted our large value engineering proposal that removed a flyover, three bridges, impacts to wetlands, and two ponds. This was accomplished by modifying the operations of northbound Jeff Fuqua Boulevard and Cargo Road through the addition of a slip ramp and the first roundabout on GOAA property.
By the Numbers
311.5K CY
Embankment
10.3K LF
Pipe Culvert
36.8K LF
Continuous Welded Track
46.4K LF
Micropile
56.6K SF
Deck waterproofing
6
Box Beam Bridges
1
Traffic Circle
2
Underpasses
1
Interchange
$85M
Project Value
Scope of Work
- Electrical & catenary
- Foundations – catenary & platform
- Landscape & wetlands
- Civil/drainage
Unique Challenges
- Constructing this work without impacting air traffic.
- Limited access to work zones.
- Working inside airport secure areas.