Fitter Interlocking & Wetland Mitigation

Rail/Transit, Rail
Bid Build
Clinton, CT
AMTRAK
Award Winner

The Middlesex Corporation was contracted by Amtrak (National Railroad Passenger Corporation) for the Fitter Interlocking and Wetland Mitigation project.

The work for this project was under a tight deadline of 21 months. In Year 1, the foundations were placed and most of the off-line civil and platform work on the railroad was completed. This included and installing an underdrain within the railroad ballast and cleaning and reconstructing existing drainage ditches as needed. In Year 2, the focus was single-track closures where catenary and track work is completed.

2023 – Safety Recognition

By the Numbers

7,469 tons
Ballast and subballast

1,106′
Drilled Shafts

1 LS (42 ea. structure)
Electrical & Catenary

4.2
Average RN – Exceeds specification requirements

$30M
Project Value

Scope of Work
  • Electrical & catenary
  • Foundations – catenary & platform
  • Landscape & wetlands
  • Civil/drainage
Unique Challenges
  • Aggressive schedule of 21 months to complete the work. Year 1 (2022) to get foundations in, and most off-line civil and platform work completed. Year 2 (2023) involves the single-track closures where catenary and track work is completed
  • Foundations (drilled shafts) completed at night in 3.5 hour work windows.