I-75 SR 93 Improvements from N of Hernando to S of CR 470
This project consisted of widening 13.5 miles of I-75 from a 4-lane to a 6-lane facility beginning north of the Hernando County Line and terminating south of CR 470, and the complete interchange reconstruction at SR 48 including ramp reconstruction, milling and resurfacing, and improvements at CR 476B/CR 673 interchange.
Improvements included roadway, earthwork, drainage, bridge, MSE walls, miscellaneous structures, guardrail, signing and pavement marking, signalization, Intelligent Transportation Systems (ITS) improvements, geotechnical, utilities, subsurface utility engineering, public involvement, and environmental permitting.
2017- Best in Construction – Interstate
2017 – Merit Award – Transportation Roadways
By the Numbers
20K T
Temporary Asphalt Pavement
450K CY
Excavation
516K CY
Embankment
270K T
Limerock Base
170K T
Superpave Asphalt Pavement
275
Drainage Structures
12K FT
MSE Walls
920K SY
Fine Grading & Sodding
$75M
Project Value
Scope of Work
- Widening I-75 from 4 to 6 lanes for 13 miles
- Demolition of existing bridges and reconstruction of new bridges in phased construction using a temporary traffic crossover
- Complete interchange reconstruction
- Ramp reconstruction with milling and resurfacing
- improvements at the interchange
Unique Challenges
- Approved ATC eliminated guardrail in each direction and the difficult maintenance of the 1:2 side slopes
- By adjusting the horizontal and vertical geometry of Ramp B, it reduced the complexity of the construction and the need to install a temporary ramp detour
- Project required the utility relocations to be coordinated by the Design Build team
Copyright ©2024