I-90 Toll Plazas Demolitions / Ramp Reconstruction
Middlesex was responsible for the removal of roadside infrastructure, six toll plaza administrative and utility buildings, toll booths, gantries, canopies, access tunnels, parking lots, and access drives no longer needed following the implementation of the I-90 All Electronic Tolling System at six plazas: Plaza 3 (Westfield), Plaza 4 (West Springfield), Plaza 5 (Chicopee), Plaza 6 (Chicopee), Plaza 7 (Ludlow) and Plaza 8 (Palmer). Included the reconfiguration of old ramps to accommodate new traffic flow. Work was accomplished under an extremely accelerated schedule.
By the Numbers
$13M
Project value
Scope of Work
- Removal of the existing six toll plaza administrative and utility buildings
- Original ramps reconfigured to accommodate new traffic flows
- Staged removal of the existing toll booths, gantries, canopies and access tunnels
- Removal of existing parking lots and parking access drives
- Reconstruction and reconfiguration of exit ramps
- Installation of new drainage and utilities
Unique Challenges
- Logistically complex project with six locations spread over 25 miles
- First stage of demolition had to be complete in 23 days; Middlesex completed in 10
- Reconstruction of all six exits simultaneously under an accelerated schedule