Orlando International Airport TKJV GMP 5S.2 – Site, Civil, & Utilities
This project covers the completed site for the South Terminal C landside terminal building, all associated access roads, and utilities.
2023 – Best Project, Airport/Transit (Southeast)
By the Numbers
155
Acres of site prep and clearing
418K CY
Embankment
36K LF
Storm drain
282
Storm structures
2
Sanitary sewer lift stations
18,650 LF
Gravity and force main sanitary sewer
21,800 LF
Water and fire system
13K LF
Communications duct banks and fiber
16.5K Tons
Asphalt paving
16.5K Tons
Asphalt paving
5.3K SY
Concrete paving
100
Peak workforce
$63M
Project Value
Scope of Work
- Grading and roadway improvements
- Maintenance of traffic for road closures during road construction.
- Concrete road pavement, milling and resurfacing and a concrete traffic separator.
- Roadway and parking lot striping, lighting and signage.
- Erosion control measures including silt fencing, floating, turbidity, barriers, and inlet protection.
- Utility improvements
Unique Challenges
- Schedule and order changes due to multiple bulletins.
- Delay of shop drawing approval process due to design changes.
- Power duct bank installed shallower in some areas which could conflict with Middlesex’s utilities including budgeted construction means and methods.
- Accelerated schedule to meet STC opening date.