Resurface & Safety Improvements Turnpike Mainline MP 260.2-MP 265.3

Paving
Orange County Florida, FL
Florida Department of Transportation
Award Winner

The Middlesex Corporation work consisted of providing all labor, materials, equipment and incidentals necessary for milling & resurfacing, landscaping, drainage improvements, pervious concrete, curb & gutter, signing, pavement marking, lighting and intelligent Transportation Systems.

2022 – Road Builder Award

By the Numbers

448K SY
Milling

67K Tons
Asphalt

17K SY
6′ Pervious Concrete Pavement

9.5K
LF Concrete Curb

2.5K
LF Shoulder Gutter

350
15′-25′ Concrete Light Pole Assemblies

$19.2M
Project value

Scope of Work
  • Turkey Lake Parking Lot: Selective clearing, relocation of palm trees, demo of curbs, asphalt, base, excavation of existing material, installation of landscaping root vaults and backfill, installation of electrical & ITS underground, backfill of islands with landscape soils, island perimeter curbs, ribbon & header curbs, 57 stone under pervious concrete layer, pavement markings for parking stalls, small & large plants, irrigation, decorative light & ITS poles, parking stops. Bridge superstructure with reinforced concrete deck on 36” FIB Girders
  • Mainline: Milling and resurfacing of 5.1 miles of four NB & SB lanes, guardrail replacement, shoulder gutter repair, single post & multi-post signs, and temporary & permanent pavement markings. and drainage storm water improvements.
Unique Challenges
  • Restrictions of Working on 1 of 10 parking sections at a time.
  • Working with previous concrete and expertise and its control of its subcontractor.
  • Wehicles traveling in excess of 70 mph near work zone emphasized safety for team.
  • 40 lane miles paved, including cross slope corrections