Middlesex is rebuilding and upgrading Tower 1 Interlocking and Cove Interlocking. Scope includes sitework, trackwork, structural, power, lighting, signals, and communication work.
Tower 1 interlocking area: (1) Replacement of trackwork. (2) Foundation & platform for a new 60ft x 10ft central instrument house. (3) Upgrading of the existing relay based signal system with a microprocessor based signal system. (4) Replacement of existing back-up power generator from 150kVA to 300kVA. (5) New lighting & replacement of floodlights. (6) Additions to the communications & security systems. (7) Replacement of trackwork & associated signal infrastructure within the Cove interlocking area.
By the Numbers
$2M
Civil Work
$13M
Track Work
$34M (35% of Project Value)
Electrical Work
$98.6M
Project Value
Scope of Work
- End of the line layover facility
- System installation
- Positive train control
- Program-wide signals and communications systems
- Electrical Signal/Systems/PTC
- Track work
- Civil Work / Drainage / Culverts
- Retaining Walls
Unique Challenges
- 5 year project – most completed during 105 weekends of closure from 10PM Friday – 6AM Monday
- No track work was allowed from December 1st to March 15th